Natural Gas Featured Project

Horseshoe Casino BGE Gas Relocation

  • Installation of a natural gas pipeline extending around a new casino site covering three city blocks in downtown Baltimore
  • 1,400 LF of 24” coated steel pipe with welded and wrapped joints
  • Deep, open-cut trenches in city streets
  • Managed contaminated ground water conditions
  • Excavation around and support of numerous existing city trunk utilities with hand tunneling underneath large storm drain box culverts
  • Managed City permitting and development of a complex traffic control plan for major thoroughfare
  • Phased construction coordinating with two nearby professional sports stadiums and adjacent casino construction activities