Natural Gas Featured Project
Horseshoe Casino BGE Gas Relocation
Installation of a natural gas pipeline extending around a new casino site covering three city blocks in downtown Baltimore
1,400 LF of 24” coated steel pipe with welded and wrapped joints
Deep, open-cut trenches in city streets
Managed contaminated ground water conditions
Excavation around and support of numerous existing city trunk utilities with hand tunneling underneath large storm drain box culverts
Managed City permitting and development of a complex traffic control plan for major thoroughfare
Phased construction coordinating with two nearby professional sports stadiums and adjacent casino construction activities