Severn River Bridge Gas Crossing
- 2,900′ of 8″ welded steel high pressure gas main pipeline with 9 expansion loops
- Fabrication, installation and painting of 172 structural steel diaphragm supports, drilled and bolted into existing bridge girders
- Innovative scaffolding system provided safe access to all work points and zero impact to bridge traffic
- 100% x-ray and field coating of pipe joints and 450 psi hydrostatic pipe testing
- 6,000’ of 8” HDPE high pressure gas main pipeline on both sides of bridge with service renewals to 28 residents
- Featured in the publication, BGE Now: https://www.bgenow.com/2021/03/11/severn-river-bridge-gas-main-project-is-something-incredible-being-built/